The purchasing process is perhaps typified by the activity of raising a purchase order – the document that tells the supplier I want this item and I want it delivered at this time. In the wrong hands, purchasing processes can be complicated and bureaucratic with intricate exchanges of information and authorization requirements. Getting to the point of raising an order and getting signed of can in some extreme examples feel like you’ve run a marathon! But as most buyers will tell you, once the purchase order has been released that is not the end of the story. What happens after the order being dispatched is as crucial, in many ways to getting the order raised in the first place.

Order Acknowledgements

An order acknowledgement is a document that is raised by the seller upon receipt of your purchase order – it signifies acceptance of your order (maybe with caveats if documented). If you had any specific commercial requirements check acknowledgements carefully as it is common practice for companies to issue acknowledgements subject to their own terms and conditions rather than the buyers!

Order acknowledgements mean

• You have a contract in place
• The supplier has my order

Its commonplace for buyers to be responsible for chasing order acknowledgements from their suppliers.

Order Amendments

Remembering that the purchase order, when acknowledged/accepted represents a formal contract between the buyer and seller, changes should not be taken lightly – however – amendments are a common example of what can occur following the purchase order being raised. Examples include:

• The buyer requires a greater quantity of parts
• The Buyer requires different parts
• The buyer requires commercial changes

Where it is decided that a new order will not be raised – amendments to an existing outstanding order will take place (but will require additional order acknowledgements from the supplier).

Expediting

One of the most common tasks is in chasing parts due delivery. Complex, mission critical parts may require a close level of planning and communications between the buyer and seller to ensure that items remain on program. In severe cases – day plans may be instigated tracking each step of the manufacturing and logistics process to ensure that the part is meeting its lead time – highlighting an early stage where parts may not be delivered to schedule.

Rescheduling

In some cases where business needs necessitate order schedules may be amended – this may be pushing requirement out to a later delivery date – or conversely – bringing the item forward. This will typically be administered in close consultation with the supplier to ensure that the revised schedule can be achieved.

Summary

Various tasks should be undertaken following issuance of the purchase order. Many of these tasks are carried out by the same buyer that raised the order – with some tasks crucial to ensure problem free continuity of supply.